Symbols for documenting and analysing work — the five ASME process-chart activity symbols, the Gilbreth therbligs used in micromotion study, and the ANSI/ISO flowchart shapes used for process and information flow diagrams.

ASME Flow Process Chart Symbols

SymbolActivityMeaning
OperationSomething is created, changed, added to, or arranged — a value-adding step, or a setup/positioning step done deliberately.
TransportationAn object, worker, or piece of equipment moves from one place to another (movement that is not part of an operation or inspection).
InspectionAn object is examined or verified for quality or quantity; no physical change is made.
DelayAn object waits before the next planned action — a temporary, uncontrolled hold (queue at a machine, batch waiting for a truck).
StorageAn object is kept and protected against unauthorised removal; retrieval requires a requisition (controlled inventory).
Combined activityTwo activities performed at the same workplace by the same operator at the same time — here operation + inspection.

On a flow process chart the analyst records, for every step, the symbol, the distance moved, the time, and the quantity. Summarising the counts of each symbol — and attacking transportation, delay, and storage first — is the core of methods improvement. An operation process chart shows only operations and inspections (the two symbols that add value or assure it); a flow process chart adds the other three plus distances and times for one component or one worker.

Therbligs — Fundamental Hand Motions

The 18 elemental motions identified by Frank and Lillian Gilbreth for micromotion analysis. Effective therbligs (those that advance the work) are targeted for speed; ineffective therbligs (search, select, position, hold, delay) are targeted for elimination.

TherbligAbbr.Type
SearchSHIneffective
SelectSTIneffective
GraspGEffective
HoldHIneffective
Transport loadedTLEffective
Transport emptyTEEffective
Release loadRLEffective
PositionPIneffective
Pre-positionPPEffective
InspectIIneffective
AssembleAEffective
DisassembleDAEffective
UseUEffective
Unavoidable delayUDIneffective
Avoidable delayADIneffective
PlanPnIneffective
Rest to overcome fatigueRIneffective
Find (locate)FIneffective

Flowchart Symbols (ANSI/ISO 5807)

SymbolNameUse
TerminatorStart or end point of a process or program.
Process / operationA processing step, action, or function.
DecisionA branch point; one input, two or more mutually exclusive outputs (yes/no).
Data (input/output)Data entering or leaving the process, medium unspecified.
DocumentOutput that is a human-readable document or report.
Predefined processA named sub-process defined elsewhere.
PreparationSet-up step that modifies a later instruction (initialise, set a switch).
Manual operationA step performed by a person without mechanical aid.
ConnectorAn on-page (or off-page) jump between flowline segments.